Toyota Land Cruiser

FJ60, FJ62 and FJ80 1980-1997 of release

Repair and car operation



Toyota Land Cruiser
+ 1. The maintenance instruction
+ 2. Maintenance service
+ 3. Engines
+ 4. Systems of cooling, heating
+ 5. Fuel and exhaust systems
+ 6. System of decrease in toxicity
- 7. Transmission
   - 7.1. A mechanical transmission
      7.1.1. Technical characteristics
      7.1.2. Removal and manual transmission installation
   + 7.2. Automatic transmission
   + 7.3. A distributing box
   + 7.4. Coupling, карданные shaft, semiaxes and leading bridges
+ 8. Brake system
+ 9. Suspension brackets and a steering
+ 10. A body
+ 11. An electric equipment
+ 12. Electroschemes


7.1.2. Removal and manual transmission installation
THE GENERAL DATA

The prevention

In procedures of a check point described more low it acts in film and established in gathering with a distributing box.


Removal

PERFORMANCE ORDER
1. Disconnect the battery from weight.
2. Turn away the lever handle, turn away screws and remove a lever cover.
3. Press on a restrictive ring in the basis of the lever (2), turning simultaneously counter-clockwise (3), and remove the lever (1 – a fabric).
4. Lift the car and establish on supports
5. Remove the bottom guard (if it is provided) and merge oil from a check point and a distributing box.
6. Remove карданные shaft (subsection 7.4.3.2 see).
7. Disconnect from a check point sockets and vacuum hoses.
8. Disconnect a cable of a speedometer and remove a starter.
9. Turn away bolts and remove the working cylinder of coupling. Take the cylinder aside.
10. Remove the lever from a distributing box.
11. Remove exhaust system pipes to provide sufficient access.
12. Will hang out the engine талью, or prop up a jack through a board. At the removed transmission the engine always should be in the hung out condition.
13. Prop up a check point the cart-jack.
14. Turn away bolts of fastening of a check point to a cross-beam.
15. Raise transmission and turn away bolts of fastening of a cross-beam to a frame, remove a cross-beam.
16. Turn away bolts of fastening of a check point to the engine (on fig. – apertures under bolts).
17. Be convinced that all necessary wires and hoses are disconnected, displace a check point back so that картер the check point has descended from pins on the block of cylinders, without supposing check point sagging on primary to a shaft.
18. Lower a check point with a distributing box.
19. Replace coupling (subsection 7.4.2 see).

Installation

PERFORMANCE ORDER
1. Installation is carried out upside-down.
2. Bolts of fastening of a check point reliably tighten.
3. After joining of wires fill a check point with oil and lower the car.
4. Establish levers.
5. Check up road performance of the car.